Cubic yards, tons and posts - estimating concrete, gravel and fence jobs from one drawing

Most site estimates come down to three conversions: feet into cubic yards, cubic yards into tons, and a line into posts and panels. Here's the math for each, with worked examples, and how KardinalEye does all three from one drawing.
Concrete: square feet to cubic yards
Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27. There are 27 cubic feet in a cubic yard. Depth is usually given in inches, so divide it by 12 first.
Worked example: a 20 × 24 ft slab, 4 inches thick.
- 4 inches ÷ 12 = 1/3 ft
- 20 × 24 × 1/3 = 160 cubic feet
- 160 ÷ 27 = 5.93 cubic yards
Add the overage you normally order for that kind of pour (your number, from your own jobs), then round to what the plant will deliver.
Gravel and stone: cubic yards to tons
Suppliers sell stone by the ton, but you measure it by volume. Work out the cubic yards the same way as concrete (area × depth ÷ 27), then multiply by your supplier's tons per cubic yard for that material. Crushed stone is often quoted at roughly 1.4 to 1.5 tons per yard, but it varies by material and moisture, so use the figure your supplier gives you and keep it in your price book.
Worked example: a 12 × 60 ft driveway, 4 inches of stone. 12 × 60 × 1/3 = 240 cubic feet, ÷ 27 = 8.9 cubic yards, × your supplier's factor.
Fence: feet to posts and sections
For each straight run: sections = run length ÷ post spacing (round up), and posts = sections + 1. Corners, ends and gates usually take heavier posts, so count them separately.
Worked example: 200 ft of fence with 8 ft spacing in one straight run. 200 ÷ 8 = 25 sections, so 26 posts. Split that same 200 feet into four sides of a yard and the corners share posts, so count per run and subtract the shared corners.
Why drawing it beats driving out
Driving out with a wheel and a tape before every bid costs a morning, and converting feet into yards, tons, posts and bags by hand is where line items go missing. KardinalEye lets you draw the job on free 1-ft aerial photos and gives you lengths, areas and counts right away. Depth, width and spacing then turn them into cubic yards, tons, gallons, posts and panels.
It covers 15 job types, including site plumbing, concrete, fencing, metal buildings, paving, landscaping, drainage and pools. Prices come from your own book (materials, labor hours, crews, waste, overhead and profit), with every number traced and a scope check. The proposal is Good / Better / Best, signed on screen, and the job tracks to paid on the build board.
Price: $120 for 30 days or $1,200 for a year, one payment, no automatic renewal, one key for the whole business. The 7-day demo is free in your browser.